Day 8: We tape and joint the walls. 1st coat. The lengths of timber on the floor are the 100 x 32 P.A.R. that we have prepared for one section of the shopfront.

charles :: Blog :: ArchivesOctober 2006October 04, 2006Day 8: We tape and joint the walls. 1st coat. The lengths of timber on the floor are the 100 x 32 P.A.R. that we have prepared for one section of the shopfront.
Posted by charles | 0 comment(s) Day 9: We start assembling the shopfronts.
Posted by charles | 0 comment(s) Day 10: Further assembly of shopfronts. Cut and fit panels to 25 x 25mm battens. Khutjo khokha moya.
Posted by charles | 0 comment(s) October 05, 2006Day 11: We assemble shopfronts. Fit panels. Khutjo khokha moya gape.
Posted by charles | 0 comment(s) October 12, 2006Day 12: The shop front is up. We will do the mouldings later.
Posted by charles | 0 comment(s) Day 13: We start the knotty pine ceiling. Secret-nailed of course. Day 14: Joint the walls second coat. Posted by charles | 0 comment(s) Day15: We start the brandered ceiling. Day 16 & 17: More rubbing down and jointing.
Posted by charles | 0 comment(s) October 18, 2006Day 18: We calculate and set out for the suspended ceiling. Fix wall the wall moulding, main tees, cross tees, and panels.
Posted by charles | 0 comment(s) Day 19: We cut the outside panels and finish the ceiling. Install the light.
Posted by charles | 0 comment(s) Day 20: We start the workshop rods for the kitchen
Posted by charles | 0 comment(s) October 31, 2006Day 21-26: We cut, edge, and assemble the carcasses for the kitchen.
Posted by charles | 0 comment(s) |