October 2006

October 04, 2006

Day 8: We tape and joint the walls. 1st coat. The lengths of timber on the floor are the 100 x 32 P.A.R. that we have prepared for one section of the shopfront.

Day8

Posted by charles | 0 comment(s)

Day 9: We start assembling the shopfronts.

Day9

Posted by charles | 0 comment(s)

Day 10: Further assembly of shopfronts. Cut and fit panels to 25 x 25mm battens. Khutjo khokha moya.

Day10

Posted by charles | 0 comment(s)

October 05, 2006

Day 11: We assemble shopfronts. Fit panels. Khutjo khokha moya gape.

Day11

Posted by charles | 0 comment(s)

October 12, 2006

Day 12: The shop front is up. We will do the mouldings later.

Day12

Posted by charles | 0 comment(s)

Day 13: We start the knotty pine ceiling. Secret-nailed of course. 

Day 14: Joint the walls second coat.

Day13

Posted by charles | 0 comment(s)

Day15: We start the brandered ceiling.

Day 16 & 17: More rubbing down and jointing.

Day14

Posted by charles | 0 comment(s)

October 18, 2006

Day 18: We calculate and set out for the suspended ceiling. Fix wall the wall moulding, main tees, cross tees, and panels.

Day15

Posted by charles | 0 comment(s)

Day 19: We cut the outside panels and finish the ceiling. Install the light.

Day16

Posted by charles | 0 comment(s)

Day 20: We start the workshop rods for the kitchen

Day17

Posted by charles | 0 comment(s)

October 31, 2006

Day 21-26: We cut, edge, and assemble the carcasses for the kitchen.

Day27+

Posted by charles | 0 comment(s)