Day 1. 11 learners start the project in the Carpentry and Joinery Workshop at Tshwane North College: Mamelodi Campus. After planning

and creating a timeline

we started the floor.

charles :: Blog :: ArchivesSeptember 2006September 21, 2006Day 1. 11 learners start the project in the Carpentry and Joinery Workshop at Tshwane North College: Mamelodi Campus. After planning and creating a timeline
we started the floor.
Posted by charles | 0 comment(s) September 22, 2006Posted by charles | 1 comment(s) September 23, 2006Posted by charles | 0 comment(s) Day 4. We fix the timber frames and start putting down the metal track to create rooms and start putting in the metal studs.
We plumb the corners and put in the rest of the metal studs.
We start the boarding.
Posted by charles | 0 comment(s) September 26, 2006Day 5: Boarding.
We also start the ceiling joists.
Bring on the frames.
Posted by charles | 0 comment(s) September 27, 2006Day 6. We install a metal frame. (Bowing is caused by the camera.)
Use the plumb rule and prepare an opening for a timber lining.
Pop rivet a stud.
Fix corner beads.
Posted by charles | 0 comment(s) September 28, 2006Day 7. We finish the openings and then we apply fibre tape to the walls.
Posted by charles | 0 comment(s) |